This incident is resolved and the Jobylon ATS is performing normally. We have changed how we prioritize background tasks and how we handle degraded responses from our calendar and email integration provider, so a disruption at a third party can no longer delay other processes in the ATS.
The Microsoft 365 incident is still ongoing. Calendar and email sync for Microsoft accounts may remain delayed or incomplete until Microsoft recovers. We recommend following Microsoft’s status page for updates: https://status.cloud.microsoft/
If you notice anything unusual, please contact support. We apologise for the inconvenience.
Posted Nov 13, 2026 - 10:48 UTC
Monitoring
The Jobylon ATS is now performing normally. We have resolved the processing backlog, and background processes such as email sending, application processing, and automated workflows are running without delays.
The Microsoft 365 incident is still ongoing, and Nylas, our calendar and email integration provider, continues to report disruption for Microsoft accounts. To keep the ATS unaffected, we have temporarily decoupled our system from these services. Calendar and email sync for Microsoft accounts may therefore remain delayed or incomplete until Microsoft recovers. Google, IMAP, and other providers are not affected.
We are monitoring the situation and will post an update once Microsoft services are restored.
Posted Nov 13, 2026 - 08:56 UTC
Identified
We have identified the cause of the slowness. Microsoft is experiencing an incident affecting Microsoft 365, which is delaying communication with Microsoft email and calendar accounts. Google, IMAP, and other providers are not affected.
Calendar and email sync for Microsoft accounts may be delayed or fail, and the resulting backlog is slowing other background processes such as email sending, application processing, and automated workflows. Core functionality remains available and no data has been lost. Delayed actions will complete once Microsoft recovers and our backlog clears. More details on https://status.cloud.microsoft/ and https://status-v3.nylas.com/
Posted Nov 13, 2026 - 08:16 UTC
Investigating
We are investigating slowness in the Jobylon ATS. Since approximately 07:15 CET, some background processes may be delayed, including email sending, application processing, automated workflows, and calendar synchronization. Core functionality remains available, but some actions may take longer than usual to complete.
Our initial findings indicate the issue may be related to disruptions at third-party email and calendar providers that we integrate with. Our engineering team is actively working on it. No data has been lost, and delayed processes will complete once the backlog clears.
We will post another update within 60 minutes, or sooner if there is a change.